HUD CoC Program Competition

Update as of September 30, 2026

The Continuum of Care (CoC) Program is designed to promote a community-wide commitment to the goal of ending homelessness; to provide funding efforts for efforts by eligible non-profit providers, local governments, and States to quickly rehouse homeless individuals, families, youth, and persons fleeing domestic violence, dating violence, sexual assault, and stalking while minimizing trauma and dislocation caused by homelessness; to promote access to and effective utilization of mainstream programs by homeless individuals and families, and to optimize self-sufficiency among those experiencing homelessness

FY 2026 CoC NOFO – Local Competition Timeline (updated Sept. 21)

  • June 1 – NOFO published by HUD
  • June 15 – Local competition opened. New and renewal project applications for FY 2026 CoC Local Competition released
  • June 16, 1:00 – 2:30 – NOFO Overview and Local Application Webinar
  • July 13  – DUE DATE – New and renewal project applications due to the CoC (closing the local application competition)
  • July 14 – July 21 – Rank & Review Committee project application review and scoring
  • July 21 – Rank & Review meeting to rank Tier 1 projects.
  • July 22 – Renewal PSH Leasing projects that did not make Tier 1 will be notified
  • July 22 – July 29 – Application timeline for Renewal PSH Leasing projects that did not make Tier 1 to write a New Project Transition Grant or a new project entirely
  • July 29 – DUE DATE – New Project Transition Grant or new project applications submitted by Renewal Leasing PSH projects due to the CoC.
  • August 3 – August 5 – Rank & Review Committee meeting to rank Tier 2 projects and finalize the priority list recommendation.
  • August 6 – CoC Governing Council vote to approve the recommended project priority list
  • September 18 – HUD reopened the FY 2026 CoC NOFO Competition
  • No later than September 23 – Applicants notified of project inclusion or rejection on the CoC Priority List
  • September 24 – DUE DATE – Deadline to submit project scoring appeals
  • September 25 – DUE DATE – Project applications included on the priority list are due in e-snaps.
  • September 29 – DUE DATE – Revisions to e-snaps project applications due (final submission)
  • No later than September 29 – Public posting of the CoC Application and Priority list
  • September 30 by 8:00 PM ET – Submission of CoC Application and Priority List to HUD

Copyright © 2025 Partners for HOME. All Rights Reserved.

Move Atlanta Forward by Giving Back!

This #GivingTuesday, Partners for HOME invites you to join us in making a meaningful impact in the lives of our neighbors experiencing homelessness.

Since 2016, we’ve partnered with the City of Atlanta and the Atlanta Continuum of Care (CoC) to achieve a 30% reduction in homelessness. This milestone is a testament to the power of collaboration and compassion.

MAKE A DIFFERENCE

WORLD HOMELESS DAY

OCTOBER 10, 2024